Location: | Mommenheim-Schwabsburg, Germany |
Execution: | Februar 2022 |
Milling depth: | 30 cm |
Factors of success: | Contaminated verge material could be permanently consolidated on site |

Location: | Bad Bergzabern, Germany |
Execution: | January 2022 |
Milling depth: | 40 cm |
Factors of success: | The stabilization of the approximately 200 m² was completed on schedule within 2 hours at night. |

Location: | Sindelfingen, Germany |
Execution: | April 2021 |
Milling depth: | 40 cm |
Factors of success: | Broadening of state road by using existing material |

|
Location: |
Dinkelsbühl, Germany |
|
Execution: |
June 2018 |
|
Milling depth: |
30 cm |
|
Factor of success: |
High bearing shoulder stabilization with material on site |

| Location: | Lichtenstein, Germany |
| Execution: |
June 2017 |
| Milling depth: | 30 cm - 7 layers |
| Factor of success: | Saving of time, costs and resources, e.g. landfill |

| Location: | Nussdorf, Germany |
| Execution: | May 2016 |
|
Milling depth: |
30 cm |
| Factor of success: |
No maceration because of water impermeability |

| Location: | Croatia |
| Execution: | July 2015 |
| Milling depth: | 30 cm |
| Factor of success: |
Permanent water impermeability, short construction period and sustainable success |

| Location: | Monterrey, Mexico |
| Execution: | February 2014 |
| Milling depth: | 20 cm |
| Factor of success: | Better values compared with conventional rolled concrete |

| Location: | Empfingen, Germany |
| Execution: | February 2009 |
| Milling depth: | None, structure 18 cm thick |
| Factor of success: | No additional preservation work required, permanently secure and sustainable |

| Location: | Bad Wildbad, Germany |
| Execution: | June 2006 |
| Milling depth: | 50 cm – 14 layers |
| Factor of success: | Saving of time, costs and resources, e.g. landfill |