REHABILITATION OF A BICYCLE TRACK

Location:

Freiensteinau, Germany

Execution:

December 2019

Milling
depth:

35 cm

Factors of success:

Unstable soil was used for the base layer.

REHABILITAION OF AN AGRICULTURAL ROAD

Location:

Frommenhausen, Germany

Execution:

December 2018

Milling
depth:

30 cm

Factors of success:

Stabilization of unstable soil, Reuse of old asphalt

REHABILITAION OF AN AGRICULTURAL ROAD

Location:

Laichingen, Germany

Execution:

May 2017

Milling
depth:

30 cm

Factors of success:

Stabilization of unstable soil

REHABILITATION OF WITH SINGLE BITUMINOUS SURFACE TREATMENT

Location: Vestenbergsgreuth, Germany
Execution: October 2016

Milling

depth:

25 cm

Factors of success:

Natural visual appearance, no soil excavation

Rehabilitation of an agricultural road with a thin asphalt surface

Location: Hüfingen, Germany
Execution: Mai 2015

Milling

depth:

30 cm

Factors of success:

Rehabilitation oft he whole road within one day

Rehabilitation of an agricultural road without surface coating

Location: Schwieberdingen, Germany
Execution: October 2014
Milling depth: 30 cm
Factors of success:

Secure, durable and environmentally friendly, saves costs

Rehabilitation of a forest road for transporting wood

Location: Bärenthal, Germany
Execution: September 2013
Milling depth: 30 cm
Factors of success:

Time saving, permanently high load-bearing capacity and stability

Construction of an access road to an industrial facility

Location: Podberezje/Novgorod, Russia
Execution: October 2010
Milling depth: 35–45 cm
Factors of success:

Frost resistance despite difficult soil conditions, road can be driven on without asphalt, cost saving